1300 517 120 Book my assessment

Solar & battery guide · ACT

Evoenergy export limits and approvals for solar and batteries in the ACT

In the ACT, Evoenergy limits how much power a home system can send to the grid. A residential system can export up to 5 kVA per phase; on a three-phase home the default since 21 February 2025 is 10 kVA in total, or 5 kVA per phase if the inverter maker confirms it can control that.

Your installer must get Evoenergy’s approval before the system goes in.

The export limits

Your supplyExport limit (from 21 February 2025)
Single-phase5 kVA
Three-phase (default)10 kVA total across all three phases
Three-phase (alternative)5 kVA per phase, if the inverter maker confirms compliance
Above 10 kVANeeds an Evoenergy network assessment; fees apply

Homes in an embedded network (some apartments and estates) may have a lower limit, set by the network’s manager.

Inverter size limits

Since 21 February 2025, Evoenergy allows up to 20 kVA of inverters per phase, including batteries, on both single-phase and three-phase sites. The old 30 kVA cap on three-phase sites is gone. On a three-phase site, a single-phase solar or battery inverter is limited to 5 kVA per phase, so Evoenergy recommends three-phase inverters there.

What the limit means for you

If your panels make more than you use and more than you can export, the extra is wasted. A battery soaks up that surplus and gives it back in the evening. That’s one reason a battery suits larger Canberra solar systems.

The approval: a Special Connection Request

Your installer lodges a Special Connection Request through Evoenergy’s online portal. Evoenergy checks the network can take your system and issues an approval letter. Evoenergy advises homeowners to ask the installer for a copy of that letter before work starts. Ask us for yours before your install day.

Adding to an existing system

When you change an existing site, for example by adding a battery, Evoenergy requires the whole site to meet its current rules. Some older inverters may need their output limited. We check this before we quote. See adding a battery to existing solar.

Let us check your home

Book an assessment. We’ll check your phase, your inverter and what Evoenergy will approve, then design to fit. More on batteries in Canberra.

Questions

Common questions

What is Evoenergy’s export limit?
5 kVA per phase for residential systems. On three-phase homes the default since 21 February 2025 is 10 kVA in total, or 5 kVA per phase where the inverter maker confirms it.
Can I export more than 10 kVA?
Only after an Evoenergy network assessment, and fees apply.
Does a battery need Evoenergy approval?
Yes. Your installer lodges a Special Connection Request for solar or battery generation, and you should get the approval letter before installation.
Who applies for approval?
Your installer, through Evoenergy’s portal. You don’t need to apply yourself.
Does going three-phase help?
It can. Evoenergy says moving to three-phase power can reduce the impact of export limits. Single-phase inverters on three-phase sites have their own 5 kVA per phase limit.
What is the biggest inverter I can install?
Up to 20 kVA per phase, including batteries, under the rules from 21 February 2025.
Will adding a battery change my existing solar?
Possibly. Evoenergy requires the whole site to meet current rules when anything changes, so some older inverters need their output limited.

Sources

Checked against these official sources in November 2026. Rules and figures change; your quote confirms what applies on the day.

Home Energy & Battery Assessment

Find out what your home actually supports.

One phone call, your roof on the screen, your bill worked through — and your numbers in writing afterwards.

Book my assessment 1300 517 120 Mon–Fri 9am–5pm AEST
CallBook my assessment